Updated October 10: FDOT now plans to close the westbound I-4 entrance ramp from Apopka-Vineland Road (State Road 535) overnight on Sunday, October 11, and Monday, October 12, from as early as 10 p.m. until 6 a.m. The last closure is expected to end the morning of Tuesday, October 13. After the closures, the ramp works differently for about four months, according to the Florida Department of Transportation.
This post first listed October 7 and 8 as the closure nights and October 11 and 12 as backup nights. FDOT updated its advisory on October 9.
This is the Exit 68 interchange, the I-4 access point for Disney Springs, the Hotel Plaza Boulevard hotels and the Lake Buena Vista area. Westbound I-4 from here heads toward the other Walt Disney World exits and Tampa.
The two official sources don't match
- FDOT's I-4 Beyond advisory (updated October 9) lists closures on both nights, Sunday, October 11, and Monday, October 12, "with the final closure ending the morning of Tuesday, October 13."
- CFLRoads.com, FDOT's Central Florida closure list, shows the closure on Sunday, October 11, and says: "If this work is not completed as scheduled, the same closure and detour will occur during the same hours on the night of Monday, October 12."
Plan for the ramp to be closed both nights. As of Saturday, October 10, neither source says the new traffic pattern has started.
The detour
FDOT's detour during the overnight closures: "Motorists will head south on Apopka-Vineland Road, turn right onto westbound World Center Drive (S.R. 536), then take the loop ramp on the right to access westbound I-4."
What changes after the overnight closures
| Before | For about four months | |
|---|---|---|
| Southbound Apopka-Vineland drivers turning onto westbound I-4 | Free-flow right-turn lane, no stopping | Dedicated right-turn lane that must yield |
| Who has priority | Northbound drivers turning left on the green arrow | |
| Southbound through lanes | Four | Three (the right-most lane becomes the turn lane) |
| Southbound drivers heading to eastbound I-4 | Right-most through lane, then merge right after the intersection |
FDOT's wording: "The existing free-flow lane to westbound I-4 will no longer be accessible. The right-most of the four southbound through lanes will become a dedicated right-turn lane to westbound I-4." Drivers turning right "will yield to motorists with the green left-turn arrow turning onto the westbound I-4 entrance ramp from northbound Apopka-Vineland Road."
For eastbound I-4, FDOT says: "Drivers who want to access the eastbound I-4 entrance ramp will use the right-most of the three through lanes, then merge right after traveling through the intersection to access the ramp."
FDOT says the setup is "expected to be in place for approximately four months while crews complete work for the ramp's final configuration."
Dates to know
- Sunday, October 11, 10 p.m. to 6 a.m.: ramp closed overnight, detour in place (both sources agree).
- Monday, October 12, same hours: ramp closed overnight per FDOT's advisory. CFLRoads lists this night only as a backup.
- Tuesday, October 13, by 6 a.m.: FDOT's expected end of the final closure.
- After the final closure: the yield-lane setup starts and runs about four months, which puts it into early 2027.
What it means on a Disney trip
- Coming from the north on Apopka-Vineland Road and heading to westbound I-4? Once the new pattern starts, you no longer get a free right turn. Get into the right lane early and expect to wait for the green-arrow left-turn traffic to clear.
- Coming from the north and heading to eastbound I-4 toward Orlando? Stay in the right-most through lane, go through the intersection, then merge right onto the ramp.
- Coming from Disney Springs or Hotel Plaza Boulevard (northbound, turning left onto the ramp)? You keep the protected green arrow.
- Leaving Disney Springs late on Sunday, October 11, or Monday, October 12? The westbound ramp may be closed. Use the World Center Drive (SR 536) detour above.
FDOT posts the detour map and project updates at I4Beyond.com/SR535. Current closures are listed at CFLRoads.com. FDOT says construction schedules can change because of weather or other conditions.
The work is part of FDOT's I-4 at Apopka-Vineland Road interchange project. We'll update this post once the new traffic pattern is in place.